Project Overview

What You Need to Know

Purpose and Need

The purpose of this project is to identify flood mitigation alternatives that will reduce surface flooding throughout the Schoonmaker Creek Watershed and reduce flood risk to properties within the Milwaukee Metropolitan Sewerage District’s (MMSD) jurisdictional reach.

Project History

The Schoonmaker Creek Watershed is roughly 1,900 acres (3.0 square miles) in the City of Wauwatosa and the City of Milwaukee. Most of the original Schoonmaker Creek has been enclosed in pipes. Only the short reach in the City of Wauwatosa between W Lloyd Street and Milwaukee Avenue remains an open channel.

The Watershed has experienced numerous heavy storm events since 1986 (when documentation began), causing flooding to streets, homes, and businesses due to the limited capacity of the enclosed system.

In 2014, the Milwaukee Metropolitan Sewerage District (MMSD) assumed jurisdiction of the Schoonmaker Creek from W Lloyd Street to the connection with the Menomonee River. MMSD requested the Southeastern Wisconsin Regional Planning Commission (SEWRPC) perform a planning study of alternative approaches to mitigate flooding within the Schoonmaker Creek Watershed. SEWRPC completed the study in 2020.

In 2022, Wauwatosa’s Common Council recommended that two (2) alternatives from the SEWRPC report be further evaluated. Alternative One was a large tunnel, bored deep underground from W Lloyd Street along N 68th St to discharge at the Menomonee River. Alternative Two was a conventional storm sewer improvement consisting of a large box culvert starting at W Lloyd St and running south along Martha Washington Drive, W Martin Drive, and N 60th Street to discharge at the Menomonee River.

In the Fall of 2024, City Staff presented Alternative Two, the conventional storm sewer, as the preferred alternative at the Community Affairs Meeting on October 15, 2024. The Common Council passed a resolution on October 22, 2024, affirming the conventional storm sewer as the least costly option.

Design and Planning

Since October of 2024, the City has completed additional modeling and engineering for improvements within the watershed areas north of Lloyd Street. City Staff have been working with MMSD to develop 30% design plans for work in MMSD’s jurisdictional reach of the Schoonmaker Creek.

The conclusion of alternative studies will identify specific construction projects, construction cost estimates, and construction phasing timelines for the City of Wauwatosa and MMSD as they prepare Capital Improvement Plans (CIPs). MMSD and City staff are working on Intergovernmental Cooperative Agreements (ICAs) to finalize roles, responsibilities, and cost-sharing for this effort.

Project Timeline

  • Timeline item 1 - complete

    March 5, 2013

    Wauwatosa's Common Council approved a resolution to request the Milwaukee Metropolitan Sewerage District (MMSD) jurisdiction March 5, 2013.

  • Timeline item 2 - complete

    March 25, 2014

    MMSD Commission approved the jurisdiction request on March 25, 2014

    • Jurisdiction covers Schoonmaker Creek from W. Lloyd St to the confluence with the Menomonee River
    • Local storm sewers, ponded areas, and sanitary sewer systems are the responsibility of the city
  • Timeline item 3 - complete

    2014

    In 2014, MMSD requested that the Southeastern Wisconsin Regional Planning Commission (SEWRPC) perform a planning study of alternative approaches to mitigate flooding within the Schoonmaker Creek Watershed.

  • Timeline item 4 - complete

    2016-2017

    Many years of work followed the request, including stakeholder and public input. Summary of results were presented to public officials on June 14, 2016 and to neighborhood associations on January 24, 2017.

  • Timeline item 5 - complete

    December 2020

    Comprehensive report with 16 alternatives was finalized by SEWRPC in December of 2020.

  • Timeline item 6 - complete

    2021-2022

    Throughout 2021 and into 2022, city staff evaluated sixteen alternatives and recommended a detailed analysis for three options.

  • Timeline item 7 - complete

    July 2022

    The Community Affairs Committee and Wauwatosa's Common Council recommended a detailed analysis of two of the 3 recommended alternatives by city staff. The third alternative, including work to the open channel portion of the watershed, was removed from consideration.

  • Timeline item 8 - complete

    Spring 2023

    In the Spring of 2023, the city hired a consulting engineer to perform the two analyses.

  • Timeline item 9 - complete

    Oct. 2024

    City staff presented final recommendations to the Community Affairs Committee on Tuesday, Oct. 15 and Wauwatosa's Common Council on Tuesday, Oct. 22. The Common Council has decided the City of Wauwatosa will be moving forward with the conventional storm sewer option.

  • Timeline item 10 - complete

    March 2025

    The City of Wauwatosa and MMSD hired a consulting engineer to expand detailed modeling and engineering concepts north of W. Lloyd Street and refine the design of the preferred alternative south of W. Lloyd Street to reduce flood risk to properties along MMSD’s jurisdictional reach.

  • Timeline item 11 - active

    Fall of 2026:

    The City and MMSD will:

    • Complete expanded modeling north of W. Lloyd St and identify future City improvement needs.
    • Complete the 30% design improvement plans for areas within MMSD’s jurisdictional reach.
    • Obtain approval of a Watercourse Management Plan for MMSD’s jurisdictional portion of the Schoonmaker Creek.
    • Identify project financing and construction phasing timelines to implement the improvements.